jouleWise

Data Centre Loop Studio/ one loop across two sites

Data centre heat,
reborn as factory heat.

A data centre turns almost every kWh its servers draw into warm water and pays to throw it away. A factory next door burns fuel for the same temperatures. Put heat pumps on the return water and the arithmetic below is what the loop is worth — to the factory, to the data centre, and to the carbon account of both.

Cooling architecture
CRAH and chilled-water loops return at 20–30 °C; the heat pump also takes load off the chillers.
Fuel displaced
Electricity the heat pumps run on
COP at this lift3.50×50 K lift from the chilled-water loop
Green heat delivered5.0 MWth40,000 MWh-th a year
Heat-pump electricity1.43 MW11,429 MWh/yr · 10% of the DC's meter
Factory energy-cost saving₹18.6 Cr/yrbefore capex and O&M
Scope 1 CO₂ avoided8,824 t/yron contracted green electricity
Heat taken off the DC3.6 MWth36% of the servers' heat · 28,571 MWh-th/yr
Chiller electricity avoided5.7 GWh/yrchilled-water hall, chiller COP 5
Cooling-tower water saved42,857 m³/yrwhere heat would have gone through wet towers
Cost of heat₹1.57/kWh-thagainst ₹6.22 on piped natural gas

₹ per kWh of useful heat

Piped natural gasη 85%
6.22 ₹/kWh-th
Heat pump on discom tariffCOP 3.50
2.43 ₹/kWh-th
Heat pump on green open accessCOP 3.50
1.57 ₹/kWh-th
Heat pump on solar blocks + storeCOP 3.50
1.14 ₹/kWh-th

Annual cost of the factory's heat

On the boiler today5 MWth × 8,000 h
24.9 ₹ Cr
On the loopheat-pump electricity only
6.3 ₹ Cr

Illustrative, not an offer. The defaults are the deck's worked example — 10 MW IT, 5 MWth at 80 °C, COP 3.5, 8,000 h — and reproduce its figures. Capex, the hydraulic interface, the tripartite heat agreement and the DC's change-control windows are outside this arithmetic; the joint baseline replaces every input with metered loop temperatures and flows.

In short/ Data Centre Loop Studio

Data Centre Loop Studio is a free calculator for the jouleWise one-loop model, in which heat pumps lift a data centre's cooling-return water into hot water and low-pressure steam for the factory next door.

Enter the IT load and PUE, the cooling-loop return temperature, the delivery temperature the factory needs, the factory's average heat demand, the fuel its boilers burn and the electricity the heat pumps would run on. The studio returns the COP at that lift, the green heat the loop can deliver, the heat-pump electricity, the factory's energy-cost saving, Scope 1 CO₂ avoided, the chiller electricity and cooling-tower water the data centre no longer spends, and the share of the data centre's heat the loop takes. The defaults reproduce the deck's worked example.

What to take away

  • Each MW of IT load releases about a MW of heat into the cooling water, continuously; a 10 MW IT hall at PUE 1.4 is about 14 MW at the meter.
  • The lift table from the deck: COP about 5 at 30 K lift, 3.5 at 50 K, 2.5 at 70 K; low-pressure steam to 120 °C at about 2.
  • Air-cooled or chilled-water halls return the loop at 20–30 °C; liquid-cooled and AI racks return at 40–50 °C, which narrows the lift to about 35 K for 80 °C delivery and lifts the COP to about 4–4.5.
  • At COP 3.5 one kWh of electricity plus 2.5 kWh from the loop gives 3.5 kWh of factory heat and 2.5 kWh of cooling the data centre no longer buys — about 6 kWh of useful heating and cooling per kWh.
  • Default worked example: 10 MW IT, 5 MWth at 80 °C, 8,000 h/yr, COP 3.5, PNG boiler at ₹55/SCM and 85% efficiency, green electricity at ₹5.50/kWh: 40,000 MWh-th delivered, 11,430 MWh of electricity, 28,570 MWh-th from the loop, ₹24.9 Cr of fuel replaced by ₹6.3 Cr of electricity, about ₹18.6 Cr/yr saving before capex and O&M, about 8,800 t CO₂ avoided, up to about 5.7 GWh of chiller electricity and about 40,000 m³ of cooling-tower water saved.

What it assumes

  • Illustrative, not an offer. Values are replaced with metered loop temperatures and flows in the baseline.
  • The chiller credit uses a chiller COP of 5 and applies where chillers would otherwise have moved that heat; water at about 1.5 litres evaporated per kWh-th rejected applies only to wet towers.
  • Green electricity is treated as zero-emission on a market basis. Capex, the hydraulic interface and the tripartite heat agreement are outside the calculator.

Questions this page answers

Why is data-centre return water such a good heat source?
It is warm, steady and available every hour of the year, unlike ambient air. The warmer the loop, the smaller the lift to the factory's temperature and the less electricity each kWh of heat needs.
Does this put the data centre's uptime at risk?
The energy centre is designed as an extra heat sink on the loop, behind an isolation plate heat exchanger with an automatic bypass. Existing towers and dry coolers stay N+1, and the data centre's supply temperature is the controlling limit.
What does the factory pay?
Under Heat as a Service, a price per kWh of heat below its current fuel cost, with no upfront capex; its boilers stay on hot standby for peaks and loads above 120 °C.
Is this operating anywhere?
Data-centre heat reuse operates abroad, mainly into district-heating networks in Northern Europe. jouleWise's claim is the integrated single-provider model for an Indian data centre and a colocated industrial heat user, under one contract.
Reviewed 2026-10-08 · jouleWisePlain-text version

What it is telling you/ read this bit

Warmer return water,
cheaper factory heat.

The loop is the source

Ambient air at 30 °C is a 50 K lift to 80 °C. A chilled-water hall returns at 20–30 °C — the same lift, with the bonus that heat is taken out before the chillers. A liquid-cooled or AI hall returns at 40–50 °C, which is a 35 K lift and a COP in the fours. Switch the cooling architecture and watch the COP, and everything downstream of it, move.

The loop also sets the ceiling

Each MW of IT load is about a MW of heat. At COP 3.5 that supports about 1.4 MWth of factory heat per MW of IT, so a 10 MW hall can carry a factory of about 14 MWth; ask for more and the rest stays on the boiler, which the saving already accounts for.

Two credits the factory never sees

Heat taken from a chilled-water loop is heat the chillers no longer move, at about a fifth of the energy; heat taken from any loop is water the towers no longer evaporate, where the heat was going through wet towers. Both belong to the data centre, and both are metered at the same boundary as the heat the factory buys.

What this does not do

No capex, no hydraulic interface design, no change-control windows, no tripartite heat agreement. Those come out of the joint baseline — loop temperatures and flows, PUE and water data, the factory's heat map — and the design that follows it.

Next/ your campus

Tell us the campus.
We’ll close the loop.