Electricity (Amendment) Rules, 2026

Captive Power & Open Access Reforms

Understanding the New Captive Framework under the Electricity Act, 2003

Transcribed from the source deck without paraphrase. Regulatory text changes: confirm applicability, jurisdiction and current status against the primary source before relying on it.

Open Access under the Electricity Act, 2003

Open Access means the non-discriminatory use of transmission and distribution systems by:

  • Generating companies
  • Licensees
  • Consumers

to transport electricity from one point to another.

Special Status of Captive Generating Plants

  • Statutory right to carry electricity to the place of captive consumption, subject to transmission availability — Section 9(2)
  • Disputes on transmission availability are decided by the Appropriate Commission

Existing Captive Requirements

A plant qualifies as Captive if:

  • 26% ownership
  • 51% captive consumption

under Rule 3 of the Electricity Rules

Why the Amendment?

  • Improve industrial competitiveness
  • Promote captive & renewable electricity
  • Reduce ambiguity and litigation over proportional consumption
  • Align rules with modern group structures

Key Reforms

  • Group companies treated as one captive user
  • Energy Storage System recognised
  • Unit-wise captive qualification for SPVs
  • 26% ownership + 51% consumption retained

AoP Framework

  • Collective compliance retained
  • Individual benefit capped at proportionate entitlement
  • Excess still counts toward plant qualification
  • 26% owner exempt from proportionate limit

Verification

  • State Nodal Agency (intra-state)
  • NLDC (inter-state)
  • Appeal mechanism introduced — Grievance Redressal Committee
  • Annual verification

CSS & Additional Surcharge

  • No CSS/AS pending verification with declaration
  • Failure: CSS + AS + carrying cost payable

Implementation

  • Most provisions effective immediately
  • Verification/AoP provisions from 1 April 2026

Business Impact

  • Simpler compliance
  • Supports renewable captive projects
  • Greater certainty
  • Reduced disputes

What it means for you/ site by site

Thresholds are
a design input.

Group captive qualification, the proportionate entitlement cap and annual verification all shape how a renewable portfolio should be structured — before any capacity is contracted.